(Created page with "Present: MA, HH, RN, AD, MR, KL, AL ==Commissioning status== *Finished scans in medium energy section *Initial issues with EMBT:MB0 power supply stopped us from taking scan t...") |
No edit summary |
||
(2 intermediate revisions by the same user not shown) | |||
Line 14: | Line 14: | ||
**We shouldn't sacrifice safety for convenience and just bump up thresholds | **We shouldn't sacrifice safety for convenience and just bump up thresholds | ||
**Rod: This requires well specified changes | **Rod: This requires well specified changes | ||
**In principle single channel can be disabled. Just have viewscreen status as trigger. | |||
**Rod: Option for more detectors to discriminate between de-focused and focused spills? Might be to complicated for immediate solution. | **Rod: Option for more detectors to discriminate between de-focused and focused spills? Might be to complicated for immediate solution. | ||
** | **Should we have threshold settings depending on mode of operation? Need to discuss with Thomas. | ||
**MA: Does cyclotron have monitors that are getting disabled from time to time? --> Unclear. | |||
==E-LINAC status== | ==E-LINAC status== | ||
Line 26: | Line 28: | ||
==AOB== | ==AOB== | ||
*AL reached out to Thomas about meeting for global reset. Will arrange meeting time when Thomas is back from vacation | |||
*After MPS re-commissioning report, AL will write up LED calibration specs | |||
*Still need to get Post-Mortem data to analyse from BLM trips. | |||
*No update on fibre. Reflector has not arrived yet. | |||
==Action Items== | |||
*AL to arrange meeting with Thomas | |||
*AL to finish MPS re-commissioning report | |||
*AL/MA to coordinate dark current scan with Thomas/Yanyun/Ops | |||
*MA/AT/AL test fibre with reflector and beam. Test position sensitivity | |||
*AL to write up LED calibration specs | |||
*MA/AL write up specs for beam enable after commissioning results. |
Latest revision as of 18:53, 25 August 2021
Present: MA, HH, RN, AD, MR, KL, AL
Commissioning status
- Finished scans in medium energy section
- Initial issues with EMBT:MB0 power supply stopped us from taking scan the week before
- Taking scans at EINJ setpoint 950 - 975 ~10.5 MeV
- Higher EINJ setting increased dark current by factor of ~3. Spill levels in medium section ~factor of 2-3 higher compared to 2020 data. In high energy section as well.
- Still need to take dark current scan to add background to thresholds
- Should also have a study of energy dependence and dark current
- 10kW was reached at 25MeV (EINJ setting ~710). No issue with BLMs tripping
- Problem really mostly with tuning procedure when beam is on view screens
- Is there a way one could implement interlock procedure that disables a particular detector when specific view screen is inserted and re-enables when the view screen is out of the beamline again?
- Presently, we're tripping when on view screens as beam is spilled and trip settings are for well-focused beam.
- We shouldn't sacrifice safety for convenience and just bump up thresholds
- Rod: This requires well specified changes
- In principle single channel can be disabled. Just have viewscreen status as trigger.
- Rod: Option for more detectors to discriminate between de-focused and focused spills? Might be to complicated for immediate solution.
- Should we have threshold settings depending on mode of operation? Need to discuss with Thomas.
- MA: Does cyclotron have monitors that are getting disabled from time to time? --> Unclear.
E-LINAC status
- 10kW was reached at 25MeV (EINJ setting ~710).
- Next goal is 10kW at 30MeV.
- Fields were measured by RPG outside of the ehall and didn't appear to increase with higher power
- RPG measured fields at the dump afterwards. ~10uSvr/hr as usual.
- On Wednesday evening energy was already increased to 27.8 MeV at 6kW. Tune wasn't ideal. Spills just at threshold limits in high energy section. AL slightly increased levels from 50nC to ~75nC to avoid trips. In high energy section we have factor of 2 safety margin before hitting 100nC in 100ms losses.
AOB
- AL reached out to Thomas about meeting for global reset. Will arrange meeting time when Thomas is back from vacation
- After MPS re-commissioning report, AL will write up LED calibration specs
- Still need to get Post-Mortem data to analyse from BLM trips.
- No update on fibre. Reflector has not arrived yet.
Action Items
- AL to arrange meeting with Thomas
- AL to finish MPS re-commissioning report
- AL/MA to coordinate dark current scan with Thomas/Yanyun/Ops
- MA/AT/AL test fibre with reflector and beam. Test position sensitivity
- AL to write up LED calibration specs
- MA/AL write up specs for beam enable after commissioning results.