*AL, MA connected all detectors in e-hall on Tuesday and tested all PMTs with LEDs except EHAT:PMT4, which had an SHV connector on LED cable in the hall instead of BNC. But label was correct. HH to replace connector after meeting.  | |||
*Also tested all LICs by ramping up voltage and checking response.  | |||
*AL changed all high energy labels on the roof and reconnected things.  | |||
*MA reconnected all Ar lines. Now have sufficient flow rate. But turned off Ar for now until we expect beam.  | |||
*Helmholz coil was installed this morning. AL, MA to install low energy detectors today. And install spare detector for diagnostics as requested by Brandon.  | |||
*After low energy detectors are installed, work in e-hall should be finished for the moment.  | |||
== Fibre ==  | == Fibre ==  | ||
Revision as of 22:48, 27 May 2021
Present: MA, RC, AD, HH, KL, RN, AL (recorder)
Second stage trip
HV BLM issue (iseg)
E-hall work
- AL, MA connected all detectors in e-hall on Tuesday and tested all PMTs with LEDs except EHAT:PMT4, which had an SHV connector on LED cable in the hall instead of BNC. But label was correct. HH to replace connector after meeting.
 - Also tested all LICs by ramping up voltage and checking response.
 - AL changed all high energy labels on the roof and reconnected things.
 - MA reconnected all Ar lines. Now have sufficient flow rate. But turned off Ar for now until we expect beam.
 - Helmholz coil was installed this morning. AL, MA to install low energy detectors today. And install spare detector for diagnostics as requested by Brandon.
 - After low energy detectors are installed, work in e-hall should be finished for the moment.
 
Fibre
- No update
 - MA to test PMT
 - Might use empty channel on module 1
 
AOB
- HH replaced broken HV connector on roof for ELBT:PMT1C.
 - AD to correct LED label in epics on driver from EHBT:PMT4 to EHAT:PMT4.
 - MA: Wiki now accessible without vpn connection. Should be ok, as documents are only linked and not uploaded. To access those one still has to use vpn.
 - AL still needs to write up doc for LED calibration. For LICs, we'll probably just use regular spills (in between targets for instance) to test LIC response in the future.
 - MA, AL to do Post-Mortem tests.
 - AD approved Martin's document in docushare.