MPSMinutes 20210520: Difference between revisions
Jump to navigation
Jump to search
(→Fibre) |
|||
Line 6: | Line 6: | ||
= Ehall work = | = Ehall work = | ||
*AL, MA finished re-routing high-energy cables and HH shortened and terminated cables on Tuesday, which took about 6hrs. Labels were attached | |||
*AL to attach new labels on roof. Also for LEDs. AL to send HH list with required labels after meeting. | |||
*MA, AL to finish Ar connections next Tuesday and get leak detector from Rick. | |||
= Fibre = | = Fibre = |
Revision as of 17:05, 25 May 2021
Present: MA, HH, KL, MR, RN, RC, AD, AL (recorder)
Second stage trip
BLM HV trip (iseg)
Ehall work
- AL, MA finished re-routing high-energy cables and HH shortened and terminated cables on Tuesday, which took about 6hrs. Labels were attached
- AL to attach new labels on roof. Also for LEDs. AL to send HH list with required labels after meeting.
- MA, AL to finish Ar connections next Tuesday and get leak detector from Rick.
Fibre
- MA to do baseline tests next week
LED calibration
- AL to write sequence of operation as base for EPICS implementation.
- Parallel ramp up of all LEDs with PMTs at voltage