MPS Minutes 20210825: Difference between revisions
		
		
		
		
		
		Jump to navigation
		Jump to search
		
				
		
		
	
No edit summary  | 
				|||
| Line 32: | Line 32: | ||
*Still need to get Post-Mortem data to analyse from BLM trips.    | *Still need to get Post-Mortem data to analyse from BLM trips.    | ||
*No update on fibre. Reflector has not arrived yet.  | *No update on fibre. Reflector has not arrived yet.  | ||
==Action Items==  | |||
*AL to arrange meeting with Thomas  | |||
*AL to finish MPS re-commissioning report  | |||
*AL/MA to coordinate dark current scan with Thomas/Yanyun/Ops  | |||
*MA/AT/AL test fibre with reflector and beam. Test position sensitivity  | |||
*AL to write up LED calibration specs  | |||
*MA/AL write up specs for beam enable after commissioning results.  | |||
Latest revision as of 18:53, 25 August 2021
Present: MA, HH, RN, AD, MR, KL, AL
Commissioning status
- Finished scans in medium energy section
 - Initial issues with EMBT:MB0 power supply stopped us from taking scan the week before
 - Taking scans at EINJ setpoint 950 - 975 ~10.5 MeV
- Higher EINJ setting increased dark current by factor of ~3. Spill levels in medium section ~factor of 2-3 higher compared to 2020 data. In high energy section as well.
 - Still need to take dark current scan to add background to thresholds
 - Should also have a study of energy dependence and dark current
 
 - 10kW was reached at 25MeV (EINJ setting ~710). No issue with BLMs tripping
 - Problem really mostly with tuning procedure when beam is on view screens
- Is there a way one could implement interlock procedure that disables a particular detector when specific view screen is inserted and re-enables when the view screen is out of the beamline again?
 - Presently, we're tripping when on view screens as beam is spilled and trip settings are for well-focused beam.
 - We shouldn't sacrifice safety for convenience and just bump up thresholds
 - Rod: This requires well specified changes
 - In principle single channel can be disabled. Just have viewscreen status as trigger.
 - Rod: Option for more detectors to discriminate between de-focused and focused spills? Might be to complicated for immediate solution.
 - Should we have threshold settings depending on mode of operation? Need to discuss with Thomas.
 - MA: Does cyclotron have monitors that are getting disabled from time to time? --> Unclear.
 
 
E-LINAC status
- 10kW was reached at 25MeV (EINJ setting ~710).
 - Next goal is 10kW at 30MeV.
 - Fields were measured by RPG outside of the ehall and didn't appear to increase with higher power
 - RPG measured fields at the dump afterwards. ~10uSvr/hr as usual.
 - On Wednesday evening energy was already increased to 27.8 MeV at 6kW. Tune wasn't ideal. Spills just at threshold limits in high energy section. AL slightly increased levels from 50nC to ~75nC to avoid trips. In high energy section we have factor of 2 safety margin before hitting 100nC in 100ms losses.
 
AOB
- AL reached out to Thomas about meeting for global reset. Will arrange meeting time when Thomas is back from vacation
 - After MPS re-commissioning report, AL will write up LED calibration specs
 - Still need to get Post-Mortem data to analyse from BLM trips.
 - No update on fibre. Reflector has not arrived yet.
 
Action Items
- AL to arrange meeting with Thomas
 - AL to finish MPS re-commissioning report
 - AL/MA to coordinate dark current scan with Thomas/Yanyun/Ops
 - MA/AT/AL test fibre with reflector and beam. Test position sensitivity
 - AL to write up LED calibration specs
 - MA/AL write up specs for beam enable after commissioning results.