Line 1: | Line 1: | ||
==BLM calibration== | |||
*AL preparing documents for requirements and specs | |||
==View screen / BLM interlocks for tuning== | |||
*AL preparing documents for requirements and specs | |||
==FLASH/Darklight effect on MPS== | ==FLASH/Darklight effect on MPS== | ||
*Email from Luca Egoriti last week: hoping to put beam on the FLASH station (the old EMBD dump) as soon as the e-linac is back in shape, and since the shielding envelope has changed we foresee higher dose rates in the ehall coming from the target/dump. Hence, we wanted to let you know since there might be some MPS work to be done to accommodate the modifications | *Email from Luca Egoriti last week: hoping to put beam on the FLASH station (the old EMBD dump) as soon as the e-linac is back in shape, and since the shielding envelope has changed we foresee higher dose rates in the ehall coming from the target/dump. Hence, we wanted to let you know since there might be some MPS work to be done to accommodate the modifications | ||
*Recommissioning required for medium and high energy section. | |||
==2nd stage trip implementation== | |||
*Final status of implementation? | |||
*What is left to do/needed? | |||
==Fibre== | |||
*Do we have PMT? | |||
*What SiPMs are we looking to buy? | |||
==AOB== |
Revision as of 17:43, 20 January 2022
BLM calibration
- AL preparing documents for requirements and specs
View screen / BLM interlocks for tuning
- AL preparing documents for requirements and specs
FLASH/Darklight effect on MPS
- Email from Luca Egoriti last week: hoping to put beam on the FLASH station (the old EMBD dump) as soon as the e-linac is back in shape, and since the shielding envelope has changed we foresee higher dose rates in the ehall coming from the target/dump. Hence, we wanted to let you know since there might be some MPS work to be done to accommodate the modifications
- Recommissioning required for medium and high energy section.
2nd stage trip implementation
- Final status of implementation?
- What is left to do/needed?
Fibre
- Do we have PMT?
- What SiPMs are we looking to buy?