MPS Minutes 20220616: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
|||
Line 1: | Line 1: | ||
MPS meeting minutes – June 16th – 2022 | MPS meeting minutes – June 16th – 2022 | ||
Present: | Present:HH, RC, KL, AD, AL, MR, MA, SR, BH | ||
Meeting commenced: 10am PT | Meeting commenced: 10am PT | ||
Meeting adjourned: | Meeting adjourned: | ||
Line 9: | Line 9: | ||
**EMBD:LIC0 indicated red on "installed" status. Maybe module wasn't seated properly? | **EMBD:LIC0 indicated red on "installed" status. Maybe module wasn't seated properly? | ||
**HH investigated this morning | **HH investigated this morning | ||
**It's fixed but unclear how this happened. Maybe during FLASH update | |||
**In future verify epics status after working on crate | |||
**Check seated status, Argon, HV, PMT current readback | |||
**Similar to optics ok, given set of detectors to be turned on. Maybe modification of the run permit | |||
**Work request | |||
**Amend document for seated status | |||
**Calibrations | |||
*Argon flow started yesterday | *Argon flow started yesterday | ||
*Keiko updated signal PV in the alarm handler and archiver for former ELBT:PMT1A now ELBT:LICSP1 (spare channel) | *Keiko updated signal PV in the alarm handler and archiver for former ELBT:PMT1A now ELBT:LICSP1 (spare channel) | ||
* | |||
===S1 to S2 delay=== | ===S1 to S2 delay=== | ||
Line 16: | Line 24: | ||
*detect mode was fixed at 10us (plus some inherent delay through the FSD and timing system ~5us). | *detect mode was fixed at 10us (plus some inherent delay through the FSD and timing system ~5us). | ||
*Delay is adjustable between 1us and 25us. Default is 10us. | *Delay is adjustable between 1us and 25us. Default is 10us. | ||
*Look for S2 trips. Log how many we get. | |||
*Brandon just started tuning and it tripped PMT1B causing S2. Dark current much higher? | |||
*EPICS indications for S1/S2 trips => Ricky to check what is indicated when at the moment and potentially adjust to avoid confusion | *EPICS indications for S1/S2 trips => Ricky to check what is indicated when at the moment and potentially adjust to avoid confusion | ||
*Maybe S1 and S2 LED. | |||
===FLASH=== | ===FLASH=== | ||
Line 26: | Line 36: | ||
the EPICS screen. Basically all existing conversion need to be increased by 100. | the EPICS screen. Basically all existing conversion need to be increased by 100. | ||
*Rod to let HH know who will be make the changes and HH will email the “updated” user manual. | *Rod to let HH know who will be make the changes and HH will email the “updated” user manual. | ||
*Ricky to '''update the conversion factors.''' | |||
*FLASH to run next week | |||
* | |||
===E-Linac status=== | ===E-Linac status=== |
Revision as of 17:24, 16 June 2022
MPS meeting minutes – June 16th – 2022
Present:HH, RC, KL, AD, AL, MR, MA, SR, BH Meeting commenced: 10am PT Meeting adjourned:
MPS status
- LIC0 trouble shooting
- EMBD:LIC0 indicated red on "installed" status. Maybe module wasn't seated properly?
- HH investigated this morning
- It's fixed but unclear how this happened. Maybe during FLASH update
- In future verify epics status after working on crate
- Check seated status, Argon, HV, PMT current readback
- Similar to optics ok, given set of detectors to be turned on. Maybe modification of the run permit
- Work request
- Amend document for seated status
- Calibrations
- Argon flow started yesterday
- Keiko updated signal PV in the alarm handler and archiver for former ELBT:PMT1A now ELBT:LICSP1 (spare channel)
S1 to S2 delay
- the delay between stage 1 trip detection to stage 2
- detect mode was fixed at 10us (plus some inherent delay through the FSD and timing system ~5us).
- Delay is adjustable between 1us and 25us. Default is 10us.
- Look for S2 trips. Log how many we get.
- Brandon just started tuning and it tripped PMT1B causing S2. Dark current much higher?
- EPICS indications for S1/S2 trips => Ricky to check what is indicated when at the moment and potentially adjust to avoid confusion
- Maybe S1 and S2 LED.
FLASH
- anything since last week’s email?
- Board modifications complete
- Still need to update epics conversion factors
- HH thinks the modified board will work for FLASH. Before I it can be install, Controls will need to change the conversion factors on
the EPICS screen. Basically all existing conversion need to be increased by 100.
- Rod to let HH know who will be make the changes and HH will email the “updated” user manual.
- Ricky to update the conversion factors.
- FLASH to run next week
E-Linac status
=> Brandon
AOB
- The beam path restrictions are not really set up to make sure BLMs are running. Only checking HV for low-energy section
- Can we implement this now for the medium and high-energy sections? Would this cause issues, when temporarily disabling detectors?