MPSMinutes 20210520: Difference between revisions

From MPS Wiki
Jump to navigation Jump to search
Line 6: Line 6:


= Ehall work =
= Ehall work =
*AL, MA finished re-routing high-energy cables and HH shortened and terminated cables on Tuesday, which took about 6hrs. Labels were attached
*AL to attach new labels on roof. Also for LEDs. AL to send HH list with required labels after meeting.
*MA, AL to finish Ar connections next Tuesday and get leak detector from Rick.


= Fibre =
= Fibre =

Revision as of 17:05, 25 May 2021

Present: MA, HH, KL, MR, RN, RC, AD, AL (recorder)

Second stage trip

BLM HV trip (iseg)

Ehall work

  • AL, MA finished re-routing high-energy cables and HH shortened and terminated cables on Tuesday, which took about 6hrs. Labels were attached
  • AL to attach new labels on roof. Also for LEDs. AL to send HH list with required labels after meeting.
  • MA, AL to finish Ar connections next Tuesday and get leak detector from Rick.

Fibre

  • MA to do baseline tests next week

LED calibration

  • AL to write sequence of operation as base for EPICS implementation.
  • Parallel ramp up of all LEDs with PMTs at voltage

AOB