MPS Minutes 20240208
MPS meeting minutes – Feb. 8th, 2024 – 10am online Present: AL (chair, recorder), SR, BH, MA, KL, BH, HH, TP, RC, MR Commenced: 10:00 am Adjourned: 10:35 am
1) Status
- E-hall is open today.
- Emergency opening on Monday. Turbine issues.
- Warm oil tank.
- One of the insulators cracked. Keep running, but need to monitor tank.
- Following up on reason for EGUN:BIAS trip due to a stage 2 trip from EABT:LIC3B. This was due to losses from EACA. Caused a dozen trips towards end of the test. But detector worked as it was supposed to.
- Observed spikes in charge reading of EABD:PMT0. Irregular. Noise pick up? Not dramatic, but noticeable regular spikes. May hint at developing problem.
- Before end of 2023 year, there was an issue with EMBD:LIC2 (Sudden trips). Did problem come back during the last months? Brandon and AL checked connections, couldn’t find any visible problem. ==> No re-occurrence since last year.
• How long will shut down be? • When is Darklight going in/out? • Expect differences with coverage when Darklight goes in • EHD line after EHDT:MB4 to the dump will be completely changed. One mode with darklight target out and one mode with darklight target in. • Darklight will need 10kW. Will it be heavily shielded? • Collimator will be installed in front of the dump. • BPMs are getting moved. Not used in the same way. • Who shuts down beam when collimator sees to much • Need similar channel. Target this in the upcoming shutdown. Modification to the daughter board. Solder 2 capacitors. And • Document to share the specs. An order of magnitude of power. Need specs from Stephanie. No CW, just pulsed. • Verify connections before shielding goes back. • Commissioning for beamloss monitors done • Run to EMBD. HV pick-up. Expect to be contacted. Number for LIC defeat in FLASH report. • 6-8 weeks shut down. Doug needs to install collimator behind the dogleg. Takes until April •
2) Interlock functionality testing
• Any time for this? • 3 BLM force functions have been completed • Do the rest during shut-down. • Mike fixed that one LED wasn’t lighting up. • Still inconsistencies in messaging, but otherwise functioning nicely
3) Simulations
- Progress from Alexey
- Need to benchmark simulations with what we see in the e-hall.
- Could use old scans/spills
- If required, do this before the BL4N collimator shut-down
4) Fibre
- No update.
5) AOB
- Ricky is working on license enforcement system related to EOCEM replacement. Started looking at logic and planning to do the testing during the shutdown.
- Calibration document
- Planning for BL4N. We have 5 FSD modules. Need 2 for the other side of the tunnel
- BLM modules (3 are in use)
- Run fibre from 1 FSD to the other FSD
6) Action Items
- AL to submit calibration document.
- SR to send specs for collimator. Needed for integration into FSD shutdown.