MPS Minutes 20220120
		
		
		
		Jump to navigation
		Jump to search
		
Meeting commenced: 10:00am Meeting adjourned: 10:36am Present: HH, MA, KL, RN, MR, RC, AD, AL
E-Linac status
- Unclear when beam will be back.
 - What are priorities once beam is back? FLASH station?
 - Hoping for more information in Friday meeting
 
BLM calibration
- AL preparing documents for requirements and specs
 - Needs to be done at reasonable background levels, i.e., not with high dark current conditions from cavities.
 - Should this go hand in hand with scan to verify coverage after a long shut down period?
 - Add flow chart for sequence of events
 - AL to implement comments for BLM calibration requirements/specs document and send out to reviewers
 - Add requirements: For instance, beam needs to be off for calibration, cavities off => procedure during downtime
 - Add Rod, Alex and Brandon as reviewer, Mike for final approval
 - Make sure to define times precisely
 - Use 2 calibration points for PMTs to verify linearity
 
View screen / BLM interlocks for tuning
- AL preparing documents for requirements and specs
 - Add requirements and table
 - 6-7 VS with 1 or 2 BLMs to be prevented from tripping
 - Be clear on definition of "disabled". Trip function should be disabled, but readback must be available.
 
FLASH/Darklight effect on MPS
- Darklight and FLASH installation complete
 - Email from Luca Egoriti last week: hoping to put beam on the FLASH station (the old EMBD dump) as soon as the e-linac is back in shape, and since the shielding envelope has changed we foresee higher dose rates in the ehall coming from the target/dump. Hence, we wanted to let you know since there might be some MPS work to be done to accommodate the modifications
 - Recommissioning required for medium and high energy section.
 - 1kW for FLASH dump in pulse mode. 1W in continuous mode. There might be extra room for BLM thresholds ==> AL to follow up with Luca E.
 - original dump design was for 500W ?
 
Fibre
- MA in contact with Hamamatsu on lead times for PMTs. Seem to be around 2-3 months.
 - 2 PMTs may be available from Conny
 - Thomas Lindner took his PMT back end of 2021
 - Thomas L. had factory/of-the-shelve fibre coupler. We may need 3D printed coupler and just buy connector. HH thinks this is possbile. Have 3D printer with black plastic available for use.
 - MA will try to get drawings from manufacturer
 
AOB
- Making LICs for BL4N once cases are down a bit
 - HH offers to be around when Phil L. shows AL and MA how to manufacturer LICs. Possible option to make the LICs in electronics shop.
 - MA to check with Phil L. if all parts are available.
 - Do we have enough for full length of tunnel?
 - Might make longer LICs depending on required position resolution
 - Tricky part might be the end caps to seal Argon connections.
 
Action Items
- AL to follow up with Luca E. on power levels for FLASH dump.
 - AL to send out document for view screen/BLM interlock requirements/specs
 - AL to implement comments for BLM calibration requirements/specs document and send out to reviewers
 - MA: What SiPMs and or PMTs are we looking to buy?
 - Fibre coupler: MA will try to get drawings from manufacturer for 3D printing option
 - MA to check with Phil L. if all parts are available for BL4N LICs.
 - 2nd stage trip implementation:
- Final status of implementation?
 - What is left to do/needed?
 
 - AL to take recommissioning scans in medium and high energy section, once beam is back.