- 20:28, 21 November 2024 Malcorta talk contribs uploaded File:IXF-RAD-MMSI-105-125-0.22-HT edA (004).pdf
- 20:28, 21 November 2024 Malcorta talk contribs created page File:IXF-RAD-MMSI-105-125-0.22-HT edA (004).pdf
- 16:45, 11 April 2024 Lennarz talk contribs created page MPS Minutes 20240411 (Created page with "==MPS Status== *Argon only turned on during force tests *Detectors in working order ==BLM force tests== ==Collimator in front of dump== *Has been installed by Doug *Next steps? *Do we have specs, to check if it can be implemented into our MPS system? ==> Stephanie ==Fibre/Simulations== *Any updates? ==AOB==")
- 14:58, 14 March 2024 Lennarz talk contribs created page MPS Minutes 20240314 (Created page with "==MPS Status== *HV and Argon off *Just collimator channel for FLASH lights up green ==Collimator in front of dump== *Do we have specs, to check if it can be implemented into our MPS system? ==> Stephanie * ==Fibre/Simulations== *Any updates? ==AOB== *Calibration over shutdown")
- 17:11, 9 February 2024 Lennarz talk contribs created page MPS Minutes 20240208 (Created page with "MPS meeting minutes – Feb. 8th, 2024 – 10am online Present: AL (chair, recorder), SR, BH, MA, KL, BH, HH, TP, RC, MR Commenced: 10:00 am Adjourned: 10:35 am 1) Status *E-hall is open today. *Emergency opening on Monday. Turbine issues. *Warm oil tank. *One of the insulators cracked. Keep running, but need to monitor tank. *Following up on reason for EGUN:BIAS trip due to a stage 2 trip from EABT:LIC3B. This was due to losses from EACA. Caused a dozen trips towards e...")
- 19:04, 2 March 2023 Lennarz talk contribs created page MPS Minutes 20230302 (Created page with "Present: BH, MA, RC, SR, MR, HH, RN, AL Commenced: 10:01am Adjourned: 10:30am ==BLM force functionality== *Roll-out done by Mike this week. *First test performed with Brandon. Forced one detector, and it was still possible to send beam *")
- 19:39, 10 February 2023 Lennarz talk contribs created page Elog Entry 2023-02-10 (Created page with "*Switched LED driver cables for EHDT:PMT2 and EHDT:PMT4 after getting no response from EHDT:PMT2 when ramping up LED. *Now, ramping up EHDT:PMT4 LED driver channel, EHDT:PMT2 responds just fine. *This means it's either an issue with the cable or the channel. *Need to investigate further")
- 00:35, 10 February 2023 Lennarz talk contribs created page Reviews (Created page with "[https://documents.triumf.ca/docushare/dsweb/Get/Document-218180 BL4N/e-Line MPS Conceptual Design Review]")
- 21:45, 20 June 2022 Lennarz talk contribs uploaded File:Arflow.png
- 21:45, 20 June 2022 Lennarz talk contribs created page File:Arflow.png
- 21:44, 20 June 2022 Lennarz talk contribs created page Turn on Argon flow (Created page with "*Go to the gas shed across the badge room *You may need a 2T85 key if the shed is closed *To initiate the Argon flow, open both Argon bottles (on your left, when entering the...")
- 21:25, 20 June 2022 Lennarz talk contribs created page Elog Entry 2022-06-20 (Created page with "*Thomas requested to change settings for EMBD:LIC2 and EMBT:LIC3 to FLASH running conditions *This means EMBD:LIC2 is turned off and EMBT:LIC3 is set from 200pC to 750pC")
- 21:01, 16 June 2022 Lennarz talk contribs created page Start up procedures (Created page with "Turn on Argon flow Bias beam loss monitors Enable beam loss monitors Calibrate beam loss monitors")
- 20:59, 16 June 2022 Lennarz talk contribs created page Start up checklist (Created page with "*Argon flow on? *Bias on? *Calibrations done? *Thresholds correct? *Detectors installed? *Detectors enabled?")
- 20:57, 16 June 2022 Lennarz talk contribs created page Checklist (Created page with "*Argon flow on? *Bias on? *Calibrations done? *Thresholds correct? *Detectors installed? *Detectors enabled?")
- 20:18, 16 June 2022 Lennarz talk contribs created page Elog Entry 2022-06-16 (Created page with "*Issues with ELBT:PMT1B tripping due to high dark current from EINJ and View screen insertion *EINJ now at 10.2 MeV. PMT1B sees ~130pC. With view screen in level is at ~275pC....")
- 16:43, 16 June 2022 Lennarz talk contribs created page MPS Minutes 20220616 (Created page with "MPS meeting minutes – June 16th – 2022 Present: Agenda: ===MPS status=== *LIC0 trouble shooting *Argon flow started yesterday *Keiko updated signal PV in the alarm handl...")
- 16:58, 10 February 2022 Lennarz talk contribs created page MPS Minutes 20220210 (Created page with "Meeting commenced: 10:00am Meeting adjourned: am Present: HH, MA, KL, RN, MR, RC, AD, AL ==E-Linac status== *First beam on Tuesday afternoon *Priority is on FLASH *Thomas sai...")
- 17:14, 20 January 2022 Lennarz talk contribs created page MPS Minutes 20220120 (Created page with "==FLASH/Darklight effect on MPS== *Email from Luca Egoriti last week: hoping to put beam on the FLASH station (the old EMBD dump) as soon as the e-linac is back in shape, and...")
- 16:56, 13 January 2022 Lennarz talk contribs created page Action Items (Created page with "*BLM calibration *BLM operating manual *View screen interlock logic *Fibre tests with beam *HV second stage trip ->final implementation *Manufacture LICs for BL4N *Online data...")
- 17:57, 23 September 2021 Lennarz talk contribs created page File:Hamamatsu-2016.pdf
- 17:57, 23 September 2021 Lennarz talk contribs uploaded File:Hamamatsu-2016.pdf
- 17:53, 23 September 2021 Lennarz talk contribs created page Fibre (Created page with "== PMT Docs==")
- 17:49, 23 September 2021 Lennarz talk contribs created page Other Documents (Created page with "==Fibre==")
- 22:30, 22 September 2021 Lennarz talk contribs created page MPS Minutes 20210902 (Created page with "== Dark current scans == *Performed dark current scans in medium energy section this week with MB5A/C and MB0 *EINJ was at setpoint 900 ~9.5 MeV *EMBT:PMT3 was mostly at 55pC,...")
- 23:13, 15 September 2021 Malcorta talk contribs uploaded File:Vs checks.pdf (VS checks, copied from excel file.)
- 23:13, 15 September 2021 Malcorta talk contribs created page File:Vs checks.pdf (VS checks, copied from excel file.)
- 19:06, 25 August 2021 Lennarz talk contribs created page MPS Minutes 20210818 (Created page with "Present: MA, HH, RN, AD, MR, KL, AL ==Commissioning status== *Finished scans in medium energy section *Initial issues with EMBT:MB0 power supply stopped us from taking scan t...")
- 18:46, 25 August 2021 Lennarz talk contribs created page MPS Minutes 20210825 (Created page with "Present: MA, HH, RN, AD, MR, KL, AL ==Commissioning status== *Finished scans in medium energy section *Initial issues with EMBT:MB0 power supply stopped us from taking scan t...")
- 23:53, 16 August 2021 Lennarz talk contribs uploaded File:2kW BLMs 3.png
- 23:53, 16 August 2021 Lennarz talk contribs created page File:2kW BLMs 3.png
- 23:51, 16 August 2021 Lennarz talk contribs uploaded File:2kW BLMs 2.png
- 23:51, 16 August 2021 Lennarz talk contribs created page File:2kW BLMs 2.png
- 23:48, 16 August 2021 Lennarz talk contribs uploaded File:2kW BLMs 1.png
- 23:48, 16 August 2021 Lennarz talk contribs created page File:2kW BLMs 1.png
- 23:41, 16 August 2021 Lennarz talk contribs uploaded File:2kW.png
- 23:41, 16 August 2021 Lennarz talk contribs created page File:2kW.png
- 23:31, 16 August 2021 Lennarz talk contribs uploaded File:Beamparameters.png
- 23:31, 16 August 2021 Lennarz talk contribs created page File:Beamparameters.png
- 23:30, 16 August 2021 Lennarz talk contribs created page Elog Entry 2021-08-16 (Created page with "*Increased thresholds on the following detectors: **EMBD:LIC2 75pC -> 185pC **EHAT:LIC2 365pC -> 515pC **EHDT:PMT2 280pC -> 560pC **EMBT:PMT3 150pC -> 450pC **EMBT:LIC3 150pC...")
- 18:36, 11 August 2021 Lennarz talk contribs created page Elog Entry 2021-07-21 (Created page with "options|View screen check.")
- 18:34, 11 August 2021 Lennarz talk contribs created page Elog Entry 2021-08-10 (Created page with "*Trying scan with EMBD:MB0 *Disabling the detectors around 5:22PM *0.001 *FC6 reading 220uA. *1kHz, 5us *Starting at –33A. *EINJ at 950 instead of 975. In terms...")
- 18:33, 11 August 2021 Lennarz talk contribs created page MPS commissioning 2021 (Created page with "{| class="wikitable" !colspan="11"|Logbook |- |'''Date''' |'''Author''' |'''Entry''' |'''Title''' |- |2021-08-10 |Annika | ElogEntry |EMBT MB0 scan...")
- 19:44, 22 July 2021 Lennarz talk contribs created page Elog Entry 2021-07-22 (Created page with "== Commissioning == *Setting up strip tool with ELBT:PMT1B, ELBT:PMT1C and ELBD:PMT0 (PMT at gun) *Putting beam on FC2 *Will use EGUN:XCB0 and ELBT:HC Helmholtz coil for steer...")
- 16:50, 8 July 2021 Lennarz talk contribs created page Procedures (Created page with "Procedure to assemble PMTs for the ARIEL MPS")
- 16:46, 8 July 2021 Lennarz talk contribs created page MPS Minutes 20210708 (Created page with "== Firmware upgrade == == Post Mortem == == E-linac activities == == Fibre work == == AOB ==")
- 22:25, 25 June 2021 Lennarz talk contribs created page Navigation (Created page with "==Access to BLMs:== From the epics start menu select MPS->Beam Loss Monitor.")
- 22:16, 25 June 2021 Lennarz talk contribs created page Electronics (Created page with "[https://documents.triumf.ca/docushare/dsweb/Get/Document-154745/ARIEL%20e-Linac%20MPS%20BLM%20Front-End%20Electronics%20Requirements.pdf ARIEL e-Linac MPS BLM Front-End Elect...")
- 22:08, 25 June 2021 Lennarz talk contribs created page Beam loss Monitors (Created page with "[https://documents.triumf.ca/docushare/dsweb/Get/Document-193864/E-linac%20BLM%20Controls%20Configuration%20Specifications.pdf E-linac BLM Controls Configuration Specifications]")
- 20:52, 24 June 2021 Lennarz talk contribs created page MPS Minutes 20210624 (Created page with "Present: HH, KL, MR, RC, RN, AD, AL (recorder) Meeting commenced: 10:02 am Meeting adjourned: 10:30am == Post-Mortem and BLM HV== *Ricky found origin of trip issue. Summary...")